Notes from the Wind Summit
Day 1 Plenary Sessions
Larry Shirley, Director of NC State Energy Office:
This was the first wind summit for the region.
There is great potential for wind in NC (specifically). There are
possibilities of ~1000 MW of wind energy in mountains and 1500 MW
off-shore. This wind potential jumps significantly if you include areas
that are limited (sounds and further off-shore).
Phil Dougherty, National Coordinator of Wind
Powering America
Wind is the fastest growing source of potential
energy. Wind projects equal economic development, but the incentives to
build wind plants are not nearly as great as other sectors. Wind
developers and advocates must have an open mind to utility companies
(coal, natural gas, oil producers)- these are the ones with the money
and ability to develop wind. Wind is still gaining rapid access in the
US- tax credits were extended until the end of 2007, which is good, but
there needs to be a more permanent solution. The continual sun-setting
results in uncertainty for many. Wind can lead to greater economic
development- jobs in construction, operations and maintenance,
manufacturing. There really is a multiplier effect when wind springs
up.
Challenges for Wind:
1)
Interconnection and access to transmission
2)
Net metering
3)
Community acceptance
4)
Fair rate for power produced
5)
Environmental impact (avian issues)
Goals:
1)
6% of all electricity by 2020
2)
32 states with greater than 20 MW production by 2015
3)
5% of federal sector electricity by 2010
Ken Mancini, PJM Interconnection
PJM has done several things to assist wind:
1)
expedited procedure for generators that are less than 20 MW
2)
collaborated with wind experts
3)
formed intermittent capacity resource working groups
4)
offers capacity credits for wind
PJM has approximately 442MW in service
throughout their service area, and approximately 452MW under contract. PJM has integrated wind through giving renewable credits to utilities.
In North Carolina, the utilities would have to be involved.
Website:
http://www.pjm.com
Rick Carson, TVA
Buffalo Mountain, just north of Knoxville, has 18
operational turbines. This was a Green Power program that began in 1999
and, originally, was focused on three main components- solar, wind, and
digester gas. They expect to see an excess in supply in the near
future. Generation Partners (a company) allow residential or business
customers to provide up to 50 kw of green power. Lightning strikes,
while not common, severely strain the technicians- it takes about 2
weeks to get a turbine running again after a strike.
Avian mortality (all numbers disputed later
though):
- 7 song birds per year
- 12 bats per year
- No raptors or endangered species have been found
dead
Website:
http://www.tva.gov
Sam J. Ervin, National Association of Regulatory
Utility Commissioners
Neither the North Carolina PUC nor the NARUC have
wind policies, per se. There are two forms of electricity distribution-
regulated and deregulated. In these traditionally regulated states (of
which NC is one), the PUC's principle job is to adjudicate disputes and
they must comply with the statutory procedures.
Three key concepts:
1)
Integrated Resource Plan (IRP)- this is the plan from the
utility. The utility must provide the estimate for their maximum load
and provide the least-cost means for serving this load. The utility
must practice forward thinking/planning. In this regard, a utility
cannot plan for possible alternative energy use- they have to choose a
transmission method that is definite. Because of this IRP, utilities
are limited in what alternative energy they can forecast to be used.
2)
Authority over certification of generating unit- Any generator
must go through this process
3)
Rate making authority- this applies to IOU's. The PUC can
determine if the cost is too high and this forces IOU's/generators to
think about whether they can recoup costs.
In states that have deregulated, it is easier to
get through the process. In regards to wind, utilities typically build
three plants: base-load, heating, and (?). In their IRP's, the
utilities say that wind is not suitable for their purposes for base-load
generation. In the IOU opinion, dispatchability is a big issue. The
utilities need the wind on demand, not just when the wind blows. The
statutes for IRP's are focused on cost- cost at the time of submission
and cost early. The IOU statements regarding wind's infeasibility have
not been challenged- if this is something that wind advocates think is
wrong (the demandability) then this must be challenged with the PUC.
Ervin says now is the time to make that case, but do it based upon the
IRP. This is really the only way the NC PUC can do anything to
strengthen renewable energy in the state.
What has the PUC done to help renewable energy
advocates?
1)
Adopted small interconnection standards (noted that this is an
important first step)
2)
Supported certification changes to make it easier for small
generators to work
3)
Keep prices as low as possible
4)
Support NC Green Power (program where customers can voluntarily
pay to support renewable energy)
Net metering will be coming to their docket soon;
interconnection was there. In regards to the Ridge Law, Ervin says that
is there for a good reason ..."just look at Sugar Top and you'll
know"...but the interpretation needs to be clarified and that can only
be done in the General Assembly. Lots of powerful opponents to it and
there are really no Democrats from the western part of the state.
Advocates need to speak to those throughout the state and make them
understand the implications of the Ridge Law and push for change from
others within the state. (Question from audience member): In Virginia,
the attorney general's statement regarding windmills would simply be
advisory- what is the deal in NC? In NC, according to Ervin, the
opinion of the attorney general is given some degree of weight. There
is absolutely nothing, however, that should prevent someone from taking
it to court and asking for a declaratory judgment.
NARUC information: Advocated for an extension of
the tax credit. NARUC is concerned with the adoption of one size fits
all statutes and legality.
Ken Jurman, Virginia Department of Mines,
Minerals, and Energy
There is a wind power development in Highland
County, Va. Class 5 wind is located within the county and the site is a
large piece of land owned by one person. The developers expect to have
38 MW of wind energy capacity- 19 turbines at 2 MW each. This amount of
wind will offset 85,000 tons of carbon dioxide/year. These turbines
will be connected through a sub-station. The county expects
$175,000-$225,000 in annual tax revenues for 20-30 years. This is a
vast improvement from what the land provides in taxes otherwise. Also,
the development will result in the creation of 1-2 permanent jobs and
various temporary construction jobs. There are concerns from
neighbors/residents about the view-shed. There are environmental
concerns (avian, habitats, etc) and residents are fearful. NIMBY is
striking hard.
Goirdan Raacke (RELI)-
Why offshore? Lack of available land, view-shed
disturbance is limited. There are existing offshore projects- mostly in
the EU (Denmark, etc).
Challenges: Engineering, greater capital costs,
higher maintenance costs- issues with ice, maintenance, etc.
Environmental issues to deal with- shipping lanes,
fishing traffic, marine life, recreational uses...And oceanfront
mansions (Cape Wind example).
Turbine specs: 3+MW, height=250 feet+, Rotor
diameter: 295-365', RPM: 8-16; 1/3-1/2 mile spacing. (182' blade
length)- Since these are 3 miles off-shore, they would appear as though
a dime in an outstretched hand. Hopeful for 40 turbines @ 3.6 MW
14 MW=44,000 homes (operational in 2008)
Project site: 8 sq. miles- the transmission
capacity is viable from the exact location.
Over 20 years, the project saves 13.5 million
barrels of oil @ $40/barrel=$540 million; @$74/barrel=$1billion fuel
savings. Avoids annual emissions of 489 tons of sulfur dioxide, 221
tons of nitrogen dioxide, and 235,000 tons of carbon dioxide (=1/2
billion car miles avoided each year)
Many regulatory reviews required- Army Corps of
Engineers, NY Dept. of State, Coast Guard, etc... Probably the first
off-shore wind project in the US- taking due care to make sure that
everything is done absolutely right.
Cape Wind project findings: positive economic and
fiscal impact, potential 600-1000 construction jobs, no adverse impact
on real estate or avian population, positive tourism effect.
Project started in 1999 with wind potential
studies. Worked with a broad coalition and variety of
wind/environmental groups- instrumental in media connections, outreach
and education. Focused on public outreach and meeting with
stakeholders- this has been crucial to success.
Summary: Offshore=higher cost and greater energy.
Offshore=vicinity to load centers. Offshore needed for RPS compliance;
great East Coast offshore wind potential; look to European experience;
and learn from Cape Cod and LI projects; dire need for public education
and importance of environmental support.
Bill Bulpitt- Georgia Tech (working with Southern
Company)
Offshore Wind Resources in the Southeast
Just started work this summer; working with
Southern Company. Feasibility started with NSF Grant. Focused on South
Atlantic Bight- 6 years of highly creditable wind data @50 meters above
ocean surface. Wind data gathering was 40 miles offshore, 50 meters
above ocean surface at 27 meter water depth. Class 4 wind power. 6
year average is 7.6 meters/second; 479 watts/meter (squared).
Hurricanes are obviously a cause of concern.
Project will have 2 MW or 3.6 MW capacity. 3.6 MW
would have capacity of 28 % and 2 MW at 38 %.
Conclusion: Offshore wind in the Southeast warrants
further studies- resource is more significant than earlier reports;
could generate economically competitive electricity. Low population
density in the area studied; potential problems etc with this. Lots of
jurisdictional issues- federal, state, and local regulations apply in
these waters. Viewshed disruption would be minimal- try to put them 7-8
miles offshore. Going to view offshore wind sites in Europe (Denmark,
UK, and Ireland)
Jennifer DeCasaro, National Council of State
Legislators
Renewable energy (and wind in particular) has
policy implications. There are stakeholders with much at stake-
developers, landowners, and utilities. Planning and permitting are an
important first step- a locale must be identified based on transmission
lines, etc. Permitting agencies vary from state to state- in some
states it's easier to get access and permission, but in others it is
impossible. Federally, there are also many agencies to deal with: FAA,
US Fish and Wildlife Service, Bureau of Land Management, and other
federal land management organizations.
Cases:
- Minnesota- Must file permit if the development
is over 5 MW.
- Oregon- Must file permit if the development is
over 35 MW and requires a certificate. This is also all done through
only one state agency.
- South Dakota- any facility, regardless of
production, must have a permit/certification.
Bonnie Ram, Energetics, Inc.
Some factors regarding off-shore wind permitting:
project size and state/federal ocean boundaries. The US Army Corps of
Engineers looks over all navigational waters and issues. Now, after the
new Energy Bill, the Mining and Minerals department may have some
control- as of right now, there is a debate between the two agencies
over who will have the control. There is a significant control exerted,
however, over the planning and permitting process by state and local
agencies. These "ground floor"organizations can really control the
whole process. Community involvement, then, is important because this
all leads to planning, acceptance, etc. There currently is no national
off-shore wind policy.
Matt Heck, Community Energy, Inc.
CEI, Inc. started in 1999. CEI was focused on
marketing, supplying, and developing wind. The value of wind in PJM
(Pennsylvania, Jersey, and Maryland) is $40-45 MWH with the cost being
$55-60 MWH.
Current Projects:
- 7.5 MW Jersey-Atlantic City project. This wind
development will be visible to 30 million tourists per year- a huge
boom to wind developments nationwide. Most are only in remote,
mountainous locations, but this one will be seen by all tourists to
Atlantic City. The foundations for the ACUA project are massive (90
feet deep) because of concerns (even if it hasn't happened) of
hurricanes. This is something that off-shore developments must be
prepared for and account for.
- 24 MW Northeast Pennsylvania- This development
will be visible from the Pennsylvania turnpike, and will house 12
turbines.
Website:
http://www.newwindenergy.com
George Sterzinger, Executive Director of Renewable
Energy Policy Project
When communities own and develop wind (i.e.
it isn't an outside developer coming in to their land) then it really
changes attitudes. People become more taken with the idea and it is
more acceptable- the NIMBY thoughts and feelings do not creep in as
much.
REPP focused on a particular question and ran a
lengthy study- the question: How do wind sites affect property values?
The general feeling and attitude among critics was that wind
developments negatively impacted property values. The study found that
wind sites and view-sheds within these sites actually increased
comparably. Approximately 80-90% of the time, view-sheds areas grew
faster than other comparable areas. This seems to imply that turbines
do not harm property values- they may not increase the value, but they
do not harm the value. The statistics simply do not support the claim
that wind farms negatively impact property values.
Mark Lotts, Virginia Wind Energy Collaborative
Engaged in a landscape classification system-
trying to find out what impact a wind map has on a local/state agency.
Curtis Smalling, Audubon Society of NC
The impact on local and total bird populations
(from wind sites) can be significant or insignificant.
Averages: 2.3-4.3 birds/turbine/year
Nocturnal migrants may be a high risk group at some
sites. Mortality averages vary depending on region, but population
estimates (of birds struck) are not statistically available everywhere.
In North Carolina, there are approximately 450+ different species of
birds- the mountains and the coast (our wind areas) are the primary
migratory routes for these birds. For wind developers and advocates, it
is imperative to consider avian impacts when designing a location and
specifications. National standards should be utilized for site surveys
and impact studies provide a thorough site study. Advocates should
think of the environmental community as stakeholders just as if they
were utilities or customers- make sure all is done as rigorously as
possible to ensure the proper steps are taken to limit avian mortality.
Jessica Kearns, Wildlife Biologist, West Inc.
Biggest issues with wind power:
1) Bird migration
2) Threatened and endangered species
3) Bats.
Sources of impact are most importantly mortality
(flying into the blades) and habitat reduction. You must site for a
possible impact- use all available resources to determine if that is a
habitat, etc. There are lots of mortality studies throughout the
nation- contrary to an earlier presentation (Buffalo Mountain) mortality
is typically 2-4 birds/turbine. Radar has been used in select locales
in the West, but there are problems- is one blip a single bird, or a
group of birds, etc? There is no correlation between target rates and
mortality.
Bat mortality at wind farms have been documented
worldwide- in the East, in particular, mortality can increase to 30-40
bats per year. Most bat mortality measured was in a 6 week period
(August-September). Storm fronts are also important to bat migration.
Lit and unlit turbines do not seem to make a difference. It is mostly
tree bats that are being killed. No bats have been found killed by
non-moving turbines; the bats are attracted to tall structures for
roosting and attracted to the movement of the blades and the sounds
produced by the turbine. Why does it seem to be a problem in the East
more than the West - Possibly because linear funneling during migration
occurs through the ridge tops, where most turbines are located.
|